BeforeEmergency structural repair · 62 tonnes steel renewed
Collision damage, bow to frame 118
Struck a quay wall in ballast. We had a survey team aboard in 5 hours and returned her to class in 19 days against a 30-day estimate.
- Vessel
- MV Northern Star
- Type
- Handysize Bulk Carrier
- Duration
- 19 days
- Year
- 2025
The vessel contacted a quay wall at low speed in ballast condition, setting in the bow plating between frames 104 and 118 and fracturing two web frames. Our superintendent was aboard within five hours of the call with a portable 3D scanner; the damage model went to LR the same evening.\n\nBecause we could crop, roll and fit plate in-house, the critical path stayed on the welding rather than on procurement. 62 tonnes of steel was renewed, the forepeak was pressure tested, and she sailed with full class 11 days ahead of the owner's worst case.